24.5 Monitoring the assessment

The assessment can be reviewed at various times throughout the project (for example, at stage end or after a release – to see if the settings on the Agilometer are happening as predicted. Any deviation between the prediction and reality as perceived by the team would result in a change to the project management or delivery process. A slider that is much further left than predicted is likely to mean that an area of risk has been created. A slider much further to the right than predicted could mean that less governance or control is needed in certain areas.