A.3 Checkpoint report

A.3.1 Purpose

A checkpoint report is used to report, at a frequency defined in the work package, the status of the work package.

A.3.2 Composition

  • Date The date of the checkpoint
  • Period The reporting period covered by the checkpoint report
  • Follow-ups From previous reports, for example action items completed or issues outstanding
  • This reporting period:
    • The products being developed by the team during the reporting period
    • The products completed by the team during the reporting period
    • Quality management activities carried out during the period
    • Lessons identified
  • Next reporting period:
    • The products being developed by the team in the next reporting period
    • The products planned to be completed by the team in the next reporting period
    • Quality management activities planned for the next reporting period
  • Work package tolerance status How execution of the work package is performing against its tolerances (e.g. cost/time/scope actuals and forecast)
  • Issues and risks Update on issues and risks associated with the work package.