A.3 Checkpoint report
A.3.1 Purpose
A checkpoint report is used to report, at a frequency defined in the work package, the status of the work package.
A.3.2 Composition
- Date The date of the checkpoint
- Period The reporting period covered by the checkpoint report
- Follow-ups From previous reports, for example action items completed or issues outstanding
- This reporting period:
- The products being developed by the team during the reporting period
- The products completed by the team during the reporting period
- Quality management activities carried out during the period
- Lessons identified
- Next reporting period:
- The products being developed by the team in the next reporting period
- The products planned to be completed by the team in the next reporting period
- Quality management activities planned for the next reporting period
- Work package tolerance status How execution of the work package is performing against its tolerances (e.g. cost/time/scope actuals and forecast)
- Issues and risks Update on issues and risks associated with the work package.
![]() |
![]() |